Marlborough College’s Theatre System

Following an annual inspection, the existing five manual raise & lower winches were found not to comply with current standards and with only 3 weeks until a pre-booked Summer school needing to use the venue, PTB were contacted and asked to assist.

Not one to walk away from a challenge, PTB carried out a site visit the following day and a week later were busy installing five new drill driver enclosed pile hoists, mounted on a new bespoke frame. Completing these were new multi groove pulleys and mounting hardware and all completing in time for the summer school to go ahead as if nothing had happened..